Guyana: Long overdue Cemetery Road Expansion Project to be completed in one week
The long overdue Cemetery Road Expansion Project of Guyana which was supposed to have been completed since last year is expected to be completed in just over one week, stated the Ministry of Public Works.
31st of July 2024
The long overdue Cemetery Road Expansion Project of Guyana which was supposed to have been completed since last year is expected to be completed in just over one week, stated the Ministry of Public Works. For the same, the authorities are aiming to add several sub-contractors, to make sure the work is done in an effective and efficient manner.
The Minister of Public Works, Juan Edghill who made a visit to the project site last week stated that four sections of the $475 million project are being undertaken simultaneously with a vision to meet the deadline and the project does not have to face any other delays.
While shedding light on the project, the Minister noted that the second bridge which is being constructed between Cemetery Road and Princess Street is expected to be completed by mid-week. Meanwhile, culverts are being installed to widen the road for four lanes of traffic at Sussex Street.
The Minister further added that these culverts will be installed with the vision of fast-tracking the works. Notably, these are being executed by sub-contractors who were recently appointed to the project and will be paid from the original contract sum which was awarded to Avinash Contracting.
Additionally, the Minister highlighted the paving works between Sussex Street and Middle Road and stated that it is also currently ongoing by Avinash Contracting.
During his visit recently, the Minister outlined the need to hire additional contractors at the expense of the main contractor with a vision to avoid any further delay in the project which has affected the flow of traffic.
Minister Edghill stated that the contractor needs to show goodwill that he can get that task done in an effective and efficient manner. He stated that if the contractor cannot show that he can get the task done, then they will have to put an additional sub-contractor to execute those jobs and pay them from his contract sum.
For the same, the ministry has also assigned a senior engineer to support the current project engineer in ensuring that the project meets the new deadline.
Latest
- National School Meals Programme rejects claims of substandard vegetarian meal in Antigua and Barbuda
-
LIAT Air Expands Caribbean Network with New Routes to Antigua and Montego Bay -
US withdraws advisory on St. Kitts and Nevis, gives green flag to its Citizenship Programme -
CARIFTA Games 2026 set to take place in Grenada from April 4-6 -
West Indies Women’s Cricket team announced for T20 series against Sri Lanka in Grenada
Related Articles
10th of December 2024
23rd of November 2024
28th of November 2024
22nd of November 2024
26th of November 2024
21st of November 2024
21st of November 2024
20th of November 2024